Landscaping Quote Template Australia: What Your Proposal Has to Say (Inclusions, Exclusions, Provisional Sums)

Most landscaping quote templates give you a blank form, not the wording that protects your margin. Here's what I put in every proposal now: scope, exclusions, provisional sums, validity and variations.

Business Tips

Late afternoon, standing in a client's backyard with a tape measure in one hand and a notebook in the other, I used to already be dreading the proposal I'd have to write that night. If you've ever gone looking for a landscaping quote template to make that part easier, you'll know what turns up. Spreadsheets, Etsy downloads and invoicing-tool forms with a spot for your logo, a few blank lines and a total at the bottom.

The form isn't the hard part. The wording is: what you're doing, what you're not doing, what's only an estimate, and what happens when things change. That's what protects your margin, and it's the bit nobody hands you. As landscapers we're islands. You never stand on site next to another landscaper reading his proposal.

Why a blank landscaping quote template doesn't save you

For years my system went like this. I'd work out my numbers, then dig through old proposals in Word for a job that looked similar. Change the words, delete the bits that didn't fit, swap the photos. Hours of it, typing with one finger. Word was my arch nemesis, to be honest.

The real problem was that copying an old proposal meant copying its gaps. If the last one didn't mention the skip bin, neither did the new one. More times than I'd like to admit, a client has accepted a quote and halfway through the job I've realised they think something's included that I never priced. That's not on them. That's on the wording.

Scope: write it the way you'd brief the guys

Not "paving to rear". Say the job is 40 square metres of exposed aggregate to the side path, a 12 lineal metre sleeper retaining wall, excavation and removal of spoil, 60 square metres of turf and 20 lineal metres of steel edging. Quantities, materials, finishes. If you're sealing the paving, say so. If you're not, say that too.

In NSW, the NSW Government says residential building work over $5,000 including GST needs a written contract. If your job counts as residential building work, a small job contract (between $5,000 and $20,000) has to include a description of the work, any plans or specifications, and the price if known. A one-liner probably doesn't cut it.

In Victoria, Consumer Affairs Victoria says a client shouldn't have to pay for variations that deal with issues you should have identified before starting. Their example is rock you could have predicted. They also say estimates need a reasonable allowance for the nature and location of the site, and on rural or steeply sloping sites you must allow for transport and access. So if it's a hand dig and barrow it in down the side of the house, that isn't a variation later. That's scope now. Same with bulking: what comes out of the ground is bigger than the hole it left, and the skip bin has to be sized for it.

Exclusions: the line that saves the argument

I reckon exclusions save a lot of arguments, and a lot of margin, just by being written down. A short list in plain words, right under the scope. Things like rock or concealed obstructions beyond the provisional sum, relocating underground services, permit fees unless listed, and repairs to existing structures.

Permits deserve their own line. The Victorian Building Authority says a retaining wall needs a building permit if it's 1 metre or higher, or near a boundary where it could damage the neighbour's property. If your wall might land there, the proposal should say who's getting the permit and who's paying.

Provisional sums and PC items, written properly

Consumer Affairs Victoria defines a provisional sum as a reasonable estimate for work you can't give a definite price for at signing, and a prime cost item as a fitting the client hasn't picked yet, or whose price isn't known. For Victorian domestic building contracts, each item has to be listed with a breakdown showing estimated quantity and unit cost. If you'll charge more than the actual cost increase, the contract has to say how you'll calculate it and the exact amount. And you have to give the client the supplier's invoice or receipt as soon as possible after you get it.

So a line might read, using made-up numbers and not a rate: "Provisional sum: removal of rock or old footings found during excavation, estimated 2 cubic metres at $200 per cubic metre, $400." Or: "PC item: feature pavers, client to select, allowance 40 square metres at $60 per square metre."

Master Builders WA makes the point that provisional sums can be blown by a significant amount, with concealed limestone or tree trunks under a sandy, clean-looking site as the example. For Queensland regulated contracts, Construct Law Group notes some contracts allow a margin on the overrun, usually up to 20% but varying by contract, applied before GST. Their example: a $1,000 PC allowance that actually costs $2,000 becomes $1,000 plus a $200 margin plus GST, so $1,320. They also suggest getting a quote for the work or material before you give the estimate.

Consumer Affairs Victoria says it's better to specify everything than lean on allowances, because these items cause disputes. I agree. Use them for the genuinely unknown, not to skip the homework.

Validity and how variations get priced

Every proposal needs a date it's good until. Material prices move and your diary fills up. I won't give you a number, because that depends on your suppliers and your workload, but pick one and put it in your terms and conditions.

Then variations. Consumer Affairs Victoria says changes must be agreed in writing, with the new price and completion date, before the work is done. There's an exemption for minor changes, where you reasonably believe there's no permit change, no delay and no more than 2% added to the original contract price. In NSW, large job contracts need variations in writing and signed by both of you. So your template should say how variations are managed and that nothing starts until it's signed.

When a client asks what discount I can do, I tell them we don't discount, but I'm happy to help change the scope. That only works if the scope was written clearly enough to change.

Check the thresholds in your state

Consumer Affairs Victoria's building contracts page says work involving more than one trade and worth more than $10,000 needs a major domestic building contract before it starts. The VBA says paving-only and planting-only contracts generally aren't domestic building work but retaining structures are, staged contracts count as one contract, and domestic building insurance applies above $16,000. In NSW, the deposit can't exceed 10%, contracts over $20,000 need a five clear business day cooling-off period, and progress payments should match work actually done, not time on the job. I'm not a lawyer, so if you're near those numbers, get your contract checked.

These days I talk the job through on my phone at the site walk and Ask Willow turns the voice notes and photos into an itemised proposal, prompting me for the stuff that belongs in scope and exclusions: soil expansion, skip bins, access and slope. It's not perfect. I still check the numbers and change something if needed. But it's a lot easier than starting from a blank Word doc at 9pm.

The takeaway

Don't go hunting for a prettier form. Fix the words. Before your next quote goes out, check it has detailed enough scope, a written exclusions list, provisional sums, a validity date, and a line on how variations are priced and signed. That's what keeps the margin you worked out on paper in the job when it's finished.